Works are progressing well at Moneypoint Power Station for our valued client ESB, with key milestones continuing to be achieved on programme.
Current progress includes:
✔️ Foundations – Complete
✔️ Below ground infrastructure – Complete
✔️ E-House foundation slab – Complete
✔️ Structural steel – Complete
🔄 Cladding and envelope works – Ongoing
🔄 External works – Ongoing
We remain on target for handover to the ESB team on 5th June.
Great progress by all teams involved in delivering the project safely and efficiently.